Skip to content | Change text size

 

Dinosaur Dreaming

2001 Excavation report

Nicholas Van Klaveren

The Flat Rocks fossil locality was excavated for a period of six weeks, from late January to early March 2001. This was one week later than the previous year and was chosen to coincide with the university holidays and to avoid the tourist season at Inverloch.

All the fossil material was collected under permit No. 10001158 of the Department of Natural Resources and Environment Victoria.

The excavation this year was moved up the beach about five metres westward toward the cliff because of the discovery of two well-preserved mammalian jaws at 185 metres East, 100 metres North during a one-day field trip during December 2000. The relative shallowness of the overlying sand at the site higher up the beach meant that the construction of girders and tarpaulins was unnecessary.

Excavation Methods

The excavation method this year continued with the use of large iron wedges and sledgehammers to remove the bulk of the fossil layer from the targeted area. Exposed specimens were removed with a diamond sawblade-equipped Stihl TS460 Cutquik. The technique of removal used last year was continued with wedges driven into the semi-continuous coal layer at the base of the Middle Sandstone Unit, then a second level extracted with the wedges driven into the Lower Sandstone Unit.

The unfossiliferous, overlying sandstone overburden was removed with two Cobra petrol-driven jackhammers. Once the majority of the overburden was removed the method, was then switched to sledgehammers and wedges so as to provide greater control to protect the underlying fossil layer from damage.

Equipment

Due to its location, the Flat Rocks fossil locality presents a number of difficulties with regard to the difference in elevation, and large waves at high tide.

For the previous three years, a construction consisting of packing material, plastic tarpaulins, steel mesh and rock bolted down iron beams was built to help exclude sand and thereby increase access time to the fossiliferous units.

A number of innovations were to be tried this year to improve the system introduced three years ago.

Solar Power Unit and Pump

In expectation of the use of the construction this year, a solar power unit and small salt-water pump were constructed.

A continuous trickle of salt-water draining from the sand surrounding the excavation area has usually necessitated the unpleasant task for a volunteer to scoop and bucket this water throughout the day.

To dispense with this onerous (and odorous) task, a 12-watt, 8-volt, photovoltaic array coupled with 18 D-cell Nickel - Cadmium batteries form a solar power unit, which is battery assisted in cloudy times and self-charging in times of low use.

This unit powers a 12-volt salt water pump housed in a filter with a stabilizing steel base plate with a total output of around 5 litres per minute, depending upon the height of the head.

Splines

An ever-present problem with the construction used in previous years is the surge of waves driving sand and seaweed beneath the edge of the tarpaulins.

Borrowing from the method of securing fly-wire netting in windows with rubber splines, large wooden splines fitted into grooves cut into the surrounding rock around the construction were to be used to secure the heavy truck tarpaulin.

Previously, heavy sandbags were used which were unreliable, being swept away and also potentially back-damaging when moved each day.

The splines were to be held down by rock bolt washers fitted over the rock anchors used to secure the girders.

Without the use of the construction this year, this new innovation will have to be tested at a future date.

Excavated Areas

A small excavation west of the fault at 185 metres East, 99 metres North, which had always been characterised by frequent jointing and small scale faults with strongly sericitised gouge, has been worked sporadically since 1997. This site was once thought to contain mostly turtle and fish remains, unexpectedly yielded two mammal jaws in a single day in December 2000.

Area A

With the decision to concentrate on this area it was necessary to remove the overlying sandstone with the petrol driven jackhammers. During the process a thin (5 centimetre) brown, oxidized carbonaceous clay layer of limited extent (40 centimetres wide) was encountered. This new unit located at 183 metres East, 101 metres North probably represents a small pool or puddle, which was exposed for some time between the major flooding events. A number of small bones were unexpectedly found in this unit and consisted of a small hollow limb and a shard of turtle carapace. A possibility that entire small animals may be preserved in this unit due to the different environment and energy of deposition warrant further investigation next year as the majority of this small layer is still exposed in the northern face of this year's excavation.

The main fossiliferous conglomerate produced specimens at a rate and quality equal to the down-slope excavations of previous years, including a further three mammal jaws.

A major development from this year's excavation was the recognition of micro-channelling within the major conglomerate units. The deeper parts of these small channels were found to yield bone concentrations ten times that of the surrounding rock. Numerous other small channels could then be discerned all throughout the fossil layer including the lower units, in which material left behind in previous years was thought to be substandard because of the paucity of specimens.

Area B & C

Minor amounts of rock were excavated at these two points and were found to contain adequate amounts of fossil material of a medium grade.

Future Excavations

In consultation with Doris Seegets-Villiers, the units containing the mammal jaws excavated this year will be pursued westward next year.

These units again outcrop at the surface and are untouched except for a few exposed bones, which have already been cut out. It is notable that these bones are found in the base of the microchannels mentioned previously.

Excavation next year will concentrate upon the wedge-shaped lower units already exposed and then follow the main units subsurface, with some removal of sandstone overburden.

The problem of inflow of water from the mass of sand filling the previous year's hole will be countered with the building of a small sandbag wall and the placement of a slotted drainage pipe with a geotextile sock. The sandbag wall will be only two or three bags in height so it is not exposed above the sand between daily excavations next year. It has also been proposed (by Marion Anderson) that the sandbags be armoured by hessian on the west side to protect against the daily shovelling out of the excavation.